Revised Date
The Revised Date of a Milestone in a Milestone Plan is the date on which the Project Manager now believes the Milestone will actually be delivered compared with the original Planned Date i.e. it reflects the current reality of the plan. The revised date is used to update the plan when the plan has been baselined, i.e. it has reached stage three (Active) of the workflow status.