Gantt Chart – Indent/Outdent rows for Summary Grouping

Indenting (Grouping) Rows Under a Summary Task 

To group rows under a Summary Task

  1. Select any set of rows — this can include Tasks, Milestones, or Summary Tasks.
  2. Right-click the selection and choose "Indent"
    or click the Indent icon (blue right arrow). 
  3. The selected rows will be moved under the Task, Milestone or Summary Task above 

       

      Outdenting (Ungrouping) Rows from a Summary Task 

      To remove rows from under a Summary Task

      1. Select any set of rows — again, can be Tasks, Milestones, or Summary Tasks.
      2. Right-click the selection and choose "Outdent"
        or click the Outdent icon (blue left arrow).
      3. The selected rows will be moved out of the nearest Summary Task above the selection.
      4. If there are no remaining child rows under the Summary Task, it will be converted to a Task 

             

            What Happens When You Indent/Outdent 

            • The system will automatically recalculate and update: 
              • Start and End dates for the affected Summary Task. 
              • All parent Summary Tasks higher in the hierarchy, if applicable. 

             

            Moving a Summary Task with Its Children 

            To move an entire Summary Task along with its child rows

            • Select only the Summary Task row (do not select the children). 
            • Then use Indent or Outdent as described above.