Gantt Chart – Auto calculating Work Fields

The Configure View Settings (cog icon) now includes two options related to Auto Calculation:


1. AutoCalc Work Estimate from Task

  • Automatically populates the Work Estimate column using the Task Allocation formula:

    • Work Estimate = Weekdays × Resources

  • Assumes at least one resource is always allocated.

  • Allows automation of Work fields without assigning specific resources.


2. AutoCalc ETC from Work Estimate

  • Automatically populates the Work ETC (Estimate to Complete) field using:

    • Work ETC = Work Estimate – Work Done

  • If not ticked, these fields must be updated manually.


Key Notes

  • These two flags are independent – each works whether or not the other is enabled.

  • Field updates appear only after auto-save completes:

    • Look for a small popup at the bottom of the screen.

    • The affected row may briefly change colour during this process.


Manual Edits and AutoCalc Interaction

  • Even with AutoCalc enabled, users can manually edit the Work fields in the table.

  • However, manual edits do not affect the Gantt chart task bars.

    • 🔁 AutoCalc is one-way only.

  • If the Gantt task bar is later modified (e.g., Resource or Date changes), AutoCalc will:

    • Recalculate and overwrite any manual values in the:

      • Work Estimate

      • Work ETC

    • (Depending on which AutoCalc flags are set.)