Gantt Chart – Auto calculating Work Fields
The Configure View Settings (cog icon) now includes two options related to Auto Calculation:
1. AutoCalc Work Estimate from Task
-
Automatically populates the Work Estimate column using the Task Allocation formula:
-
Work Estimate = Weekdays × Resources
-
-
Assumes at least one resource is always allocated.
-
Allows automation of Work fields without assigning specific resources.
2. AutoCalc ETC from Work Estimate
-
Automatically populates the Work ETC (Estimate to Complete) field using:
-
Work ETC = Work Estimate – Work Done
-
-
If not ticked, these fields must be updated manually.
Key Notes
-
These two flags are independent – each works whether or not the other is enabled.
-
Field updates appear only after auto-save completes:
-
Look for a small popup at the bottom of the screen.
-
The affected row may briefly change colour during this process.
-
Manual Edits and AutoCalc Interaction
-
Even with AutoCalc enabled, users can manually edit the Work fields in the table.
-
However, manual edits do not affect the Gantt chart task bars.
-
🔁 AutoCalc is one-way only.
-
-
If the Gantt task bar is later modified (e.g., Resource or Date changes), AutoCalc will:
-
Recalculate and overwrite any manual values in the:
-
Work Estimate
-
Work ETC
-
-
(Depending on which AutoCalc flags are set.)
-